Analysis of the Causes of Delays in Construction Projects at the XYZ Resort Bali Project

Authors

  • Ikhsan Setiawan Department of Civil Engineering, Faculty of Engineering Narotama University Surabaya, Jalan Arif Rahman Hakim 51, Surabaya
  • Rooslan Edy Santosa Department of Civil Engineering, Faculty of Engineering Narotama University Surabaya, Jalan Arif Rahman Hakim 51, Surabaya
  • Fredy Kurniawan Department of Civil Engineering, Faculty of Engineering Narotama University Surabaya, Jalan Arif Rahman Hakim 51, Surabaya
  • Nyoman Agus Sandika Purnaman Department of Civil Engineering, Faculty of Engineering Narotama University Surabaya, Jalan Arif Rahman Hakim 51, Surabaya

Keywords:

Construction Projects, Delay Analysis, Resort Project Delays

Abstract

A construction project is a series of interrelated activities to achieve certain objectives (building or construction) within a certain time, cost and quality limitation. Delay in a project is a situation where the project cannot be completed within the planned time. The construction project at the XYZ Resort Bali project, in construction, occurred delays due to disputes. The disputes are caused by several factors between stakeholders, where each stakeholder has various and different problems. The purpose of this study is to identify and analyze the causative factors that contribute to delays in construction projects at the XYZ Resort Bali Project and provide suggestions or determine mitigation measures to overcome them. The method used is a quantitative approach in the form of literature studies, data collection through surveys, data analysis and conclusions. The survey questionnaire was designed based on the factors identified from previous research by determining as many as 6 aspects of the study with 45 types of causes or factors that contributed to project delays. Data analysis was carried out quantitatively descriptive of the delay factor variables from the questionnaire results. The questionnaire data was tested for validity and reliability, then analyzed using the fishbone diagram approach and the House of Risk method to determine the main factors that contribute to project delays and determine mitigation measures to overcome delays in project completion.

Downloads

Download data is not yet available.

References

Arditi, D. dan Patel, B. K. 1989. “Impact Analysis of Owner?Directed Acceleration.” Journal of Construction Engineering and Management (ASCE - America Society of Civil Engineers) 115.

Dewi, A. A. Diah P. 2019. “Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Gedung Di Kabupaten Karangasem.” Jurnal Ilmiah Teknik Sipil · A Scientific Journal Of Civil Engineering 79–87.

Harold Kerzner, PH. D. 2009. “Project Project Management Management Project Project Management Management A Systems Approach To Pl Anning, Scheduling, And Controlling.” John Wiley & Sons, Inc., Hoboken, New Jersey. Retrieved January 5, 2022 (http://www.mim.ac.mw/books/Kerzner’s Project Management A Systems Approach...10thed.pdf).

Kraiem, Zaki M., and James E. Diekmann. 1989. “Closure of ‘ Concurrent Delays in Construction Projects ’ by Zaki M. Kraiem and James E. Diekmann (December, 1987, Vol. 113, No. 4).” Journal of Construction Engineering and Management 115(2):337–38. doi: 10.1061/(ASCE)0733-9364(1989)115:2(337).

Kurniawan, F. 2015. “Jenis Sengketa Yang Sering Terjadi Pada Proyek Konstruksi Di Surabaya.” 227–232.

Kusnadi, E. 2011. “Fishbone Diagram Dan Langkah-Langkah Pembuatannya – Blog Eris.” Retrieved January 5, 2022 (https://eriskusnadi.com/2011/12/24/fishbone-diagram-dan-langkah-langkah-pembuatannya/).

Mario Coccia. 2017. “The Fishbone Diagram to Identify, Systematize and Analyze the Sources of General Purpose Technologies.” The Fishbone Diagram to Identify, Systematize and Analyze the Sources of General Purpose Technologies 4(4):291–303. doi: 10.1453/JSAS.V4I4.1518.

Proboyo Budiman. 1999. “(PDF) Keterlambatan Waktu Pelaksanaan Proyek Klasifikasi Dan Peringkat Dari Penyebab-Penyebabnya.” 49–58. Retrieved January 5, 2022 (Https://Www.Researchgate.Net/Publication/38101011_Keterlambatan_Waktu_Pelaksanaan_Proyek_Klasifikasi_Dan_Peringkat_Dari_Penyebab-Penyebabnya).

Pujawan, I. Nyoman, and Laudine H. Geraldin. 2009. “House of Risk: A Model for Proactive Supply Chain Risk Management.” Business Process Management Journal 15(6):953–67. doi: 10.1108/14637150911003801.

Remi, Fahadila F. 2017. “Kajian Faktor Penyebab Cost Overrun Pada Proyek Konstruksi Gedung.” Jurnal Teknik Mesin 6(2):33. doi: 10.22441/jtm.v6i2.1187.

Saputra, Ramdhan Yundra, and Imam Baihaqi. 2018. “Penggunaan Metode House Of Risk Untuk Analisis Faktor Keterlambatan Dan Penyusunan Strategi Penanganan: Studi Kasus Pembangunan Mall.” Accounting and Management Journal 1(2). doi: 10.33086/amj.v1i2.78.

Taurano, Galih Adya, and Sarwono Hardjomuljadi. 2013. “Analisis Faktor Penyebab Klaim Pada Proyek Konstruksi Yang Menggunakan Fidic Conditions Of Contract For Plant And Design Build.” Konstruksia 5(1). doi: 10.24853/JK.5.1.